Highlighting the start of foundation work both on stands in the north and the south exterior walls; should also highlightthat once the foundation of the exterior walls have been continued execution of pile caps and walls from elevation + 0.00.
Advances executing the corresponding horizontal structure slabs level 4 elevation + o, oo, low comb zone and zone boxes slabs, dimension+3.02 m.
In parallel with the above work, it continues with the execution of supports, walls, drainage and waterproofing and exterior surface of walls.