Mounting stands belonging to the high bleachers begins; these works are started in the north; parallel progress is made in making tiered grandstand.
Continue to run the remaining units of work they structure including in the perimeter walls of concrete, walls vomitoria high bleachers, slabs levels of +21.78 m, portagradas porches, slabs coronation low bleachers, scoreboards slabs.
Progress is being made in implementing factory-based partition block, and in air-conditioning and electricity plants parking’s.