In this January has increased the pace of work significantly; working on numerous construction units, namely:. foundation of low stands, stands portagradas low beams, horizontal slabs structure dimension +5.12 m and +6.40 m, the latter belonging to the overhang of high stands.
In parallel working on the implementation of vertical structures, supports and walls in areas north and south.
Continue earthworks for the emptying in central belonging to the elliptical axis of the field