Highlight the start of the foundation work of tunnel wall in this area, and north exterior wall arm.
It has been finished ring 2 level post-tensioned slabs; at the top level is only a portion of post-tensioned to run.
Advancing at remarkable pace of implementation of both the cantilever slabs middle stands as at level 4, level zero.