To emphasize the work done in the general cover of the stadium corresponding to the beginning of the installation of the gutter, and to the completion of the assembly of the structure of the canopy; at the same time progress is made in covering the fiberglass membrane cover.
The foundations, CPI-7 deep foundations, of the mast of the Club flag have been executed.
Finishing works are continuing at a good pace, including the installation of false ceilings in Vips expansion boxes, vertical cladding and the execution of floors.
The assembly of the seats has begun in the middle stage.
As for the various facilities, advances are made in the installation of ducts and air conditioning and ventilation equipment, PCI extinction pipes, data cabling and telecommunications.