Highlight the start of the execution wrought level 3 elevation -4.20 m. , -2 Ceiling basement, north, advancing at a rapid pace the implementation of Level 2 floors, having reached southeast area, all these forged respond to post-tensioned slabs typology, a typology that still has significant advantages over conventional reinforced concrete structures, both in terms of functionality, and financially.
Continue the implementation of supports and walls level 2-3, in north and southeast.
Ends sanitation, pending closing the perimeter ring at several points.
Paving work in progress area under comb.
Ments recent piles under low stands were decapitated.