In this month of November it is necessary to emphasize the complete closing of the compression ring, with the assembly of the last of the modules.
The assembly work on the connectors of the inner traction rings, both upper and lower, extended from circumferential cables and embulonado of radial cables.
In the urbanization begins the execution of the different structural elements that house the ventilation of the car parks, and the demolitions in quota +0.00 in facade west.
In relation to the other work units, the corresponding to internal divisions at different levels, coatings, waterproofing, soles, and stepped.