Continued implementation of the foundation based on concrete pile and pile caps in south.
Anchors of the screen are made up of the first dimension platform - 4m.
Begin using the new ramp to work and consequent removal of land belonging to the starting ramp.
Collection of material wall formwork, rebar supports and walls, wells and sanitation collectors buried starts, have been punctured several northern brackets for later formwork and concreting.