Are many different jobs in parallel and simultaneously have run along this March, among which portagradas beams running north zone, the major breakthrough in walls and supports with subsequent execution of slabs, as both post-tensioned slabs on several levels and different sectors are being included slabs for closing gaps in existing building comb.
Selective demolitions are continuing within the corresponding comb stairwells and access holes for lower tier west facade.
They are doing the work of clearing low comb, and connection of the new with the existing network.