Work continues mounting stands, high and low bleachers, and continues with making high-stands bleachers.
Highlighting the completion of the execution of porticos high stands.
They are making good progress work structure: perimeter concrete walls closing the second ring, upper bounds slabs, walls vomitoria, and staircases.
Continues execution of partition-based factory block, and in air-conditioning and electricity plants parkings.