The assembly of the bench structure has begun in a high stand, corresponding to the seats of said stand, whose installation will be imminent.
The canopy of the cantilevered exterior canopy is advanced towards the southeast façade; In parallel work is done both in the covering based on radial panels, and in the assembly of the speaker balconies in the tangential inner walkway of the lower traction ring.
Work continues on the lining of the various facades, both in Enlargement and in Peineta.
In the accesses to the west facade of the building, we work in the execution of the three nuclei of access stairs of quota -4.50 to +0.00.