• This month is a very special date for all of us who have collaborated in some way in the lifting of the Wanda Metropolitan Stadium, since it is known that on September 16, 2017 the long-awaited...

  • To emphasize that in the field of soccer is working in the completion of the facilities corresponding to the sanitation, drainage, irrigation, heating system, with the forecast to begin imminently...

  • Throughout this month of July, it is worth mentioning the beginning of the work of conditioning the playing field, by compaction and execution of different parcels of gravel that make up the field...

  • To emphasize the work done in the general cover of the stadium corresponding to the beginning of the installation of the gutter, and to the completion of the assembly of the structure of the...

  •  
    The assembly of the seats has begun in high stand.
    In urbanization works in the perimeter sanitation to the stadium, and in the west facade, +0.00, in the waterproofing of the floor...

  • The assembly of the bench structure has begun in a high stand, corresponding to the seats of said stand, whose installation will be imminent.
    The canopy of the cantilevered exterior canopy...

  • Highlight the beginning of the work of the outer cantilever deck, Canopy, steel overhang structure with different sections on each axis, creating a free form element.
    This outer overhang...

  •  
    The hoisting of the deck is terminated, with the successful lifting of the second drive ring.
    Following the hoisting, the assembly of the cover covering membrane based on panels of...

  • Spectacular lifting operation of the first of the traction rings of the cover, upper ring. This operation known as "the big lift" consisted in the tensioning of the radial cable assembly using...

  • In this month of November it is necessary to emphasize the complete closing of the compression ring, with the assembly of the last of the modules.
    The assembly work on the connectors of the...

  • It begins the assembly of the structure of the compression ring in Peineta, having reached the definitive points of support on the existing building.
    In parallel, they have started the...

  • Completing the assembly of the structure of the compression ring expansion zone; It is to run the assembly portion covering the Peineta, scheduled for completion in the near future.
    ...

  • Progressing as planned assembly modules compression ring general cover, reaching the Peineta; the installation was performed from east facade facade facing north.
    It works on the execution...

  • General deck: highlight the start of assembly thereof, with the hoisting of the first module of the metal structure of the compression ring in east facade.
    Area both inside Peineta...

  • Highlight the start of collection and assembly of several corresponding to the metal structure which integrates the compression ring of the general cover modules.
    the assembly work stands...

  • Throughout the month of May there have been significant advances in different work units.
    You have completed the assembly stands high stands; They have begun the rehabilitation of bleachers...

  • They have begun the work floor pan and -9.54 -11.20 m levels in parking areas and machine rooms, concrete floors run with surface treatment.
    Progress is being made in implementing factory-...

  • Progress is being made in the implementation of several of the 16 batteries cover general support in building Extension.
    Work continues mounting stands in the three grandstands, low, medium...

  • It works on assembly stands in the middle and low stands; It is continued making high-stands bleachers.
    Highlight the start of the first phase of concreting the piles of support for general...

  •  
    Work continues mounting stands, high and low bleachers, and continues with making high-stands bleachers.
    Highlighting the completion of the execution of porticos high stands.
    ...

  •  
    Mounting stands belonging to the high bleachers begins; these works are started in the north; parallel progress is made in making tiered grandstand.
    Continue to run the remaining...

  • Highlight the completion of manufacture of the stands belonging to the middle stands, as well as progress in assembling them, and the start of production of the stands high stands.
    Upon...

  • Work continues mounting stands, high and low bleachers, and continues with making high-stands bleachers.
    Highlighting the completion of the execution of porticos high stands.
    They are...

  • Assembly starts in the middle stands stands in moving towards the north east.
    They have started building work and facilities in the basement -1 y - 2.
    In outdoor area access tunnels to...

  • Collection of environmental stands in center field stands for his impending assembly begins.
    Highlight the start of the implementation of both the inner perimeter wall of the low stands and...

  • It is remarkable pace advances in manufacturing stands and medium stands parallel to this work continues the execution of the remaining units of the structure, reaching heights of housing support...

  • Highlight the start of production of prefabricated stands for the middle stands; work is continuing on this land emptied of access tunnels to the parking area of the stadium, and the vertical...

  • Highlight the start of units corresponding to the structure of beams portagradas stands high in northern work.
    It continues with the structure of access tunnels, having executed vertical...

  • In this month they have completed the foundation work, pile caps and tie beams of portagradas low stands, and the horizontal structure, dimension slabs +4.20 m., Corresponding to zone boxes....

  • Highlighting the progress of the corresponding horizontal structures slabs, having reached in northeast elevation +8.40 m, height of access to the upper deck,
    Continue the remaining work,...

  • In this January has increased the pace of work significantly; working on numerous construction units, namely:. foundation of low stands, stands portagradas low beams, horizontal slabs structure...

  • Highlighting the start of the share of beams belongs to low stands in northeast corner structure.
    Continue both foundation works with the execution of pile caps belonging to low stands, as...

  • After the foundation of the lower stands, deep pile foundation based on CPI-6; work decapitated in northern arm of piles and pile caps therefore begin execution.
    Work is progressing...

  • Highlighting the completion of the share of slabs zone boxes, elevation +3.02, between the lower ends of stands high horizontal structure, and level 5, elevation +4.20 m., And the beginning of...

  • Emphasize that once the structure portagradas middle stands, has closed the ring slab level 4 elevation +0.00 m; typology slabs this level reflect both post-tensioned slabs and slabs.
    ...

  • Highlighting the start of foundation work both on stands in the north and the south exterior walls; should also highlightthat once the foundation of the exterior walls have been continued...

  • Work is progressing pilot for exterior foundation walls, pile running up to 50 ml. excavation; has begun headed thereof encepados excavation and concreting thereof.
    Implementation of the...

  • Highlight the start of the foundation work of tunnel wall in this area, and north exterior wall arm.
    It has been finished ring 2 level post-tensioned slabs; at the top level is only a...

  • Closed rings post-tensioned slabs and armed levels 2 and 3, both in northwest; good progress implementing environmental portagradas beams stands, having started in the same south, and continuing...

  • Highlighting the scope of the zero bound on north, having started running slabs at that level; with respect to post-tensioned slabs stress levels lower bounds on the north end of the ring level 2...

  • Are many different jobs in parallel and simultaneously have run along this March, among which portagradas beams running north zone, the major breakthrough in walls and supports with subsequent...

  • Implementing portagradas beams and beams belonging to hang wrought Level 4 + 0.00 dimension starts in north.
    Work continues post-tensioned slabs at levels 2 and 3, leaving only two portions...

  • Note that it has reached the level 4 elevation +0.00 , north zone , with building walls and supports , in the north have begun work extrados wall waterproofing for further landfill .
    ...

  • Work continues execution level forged 3 -4.20 m elevation, basement ceiling -2 north,. Making good progress executing forged Level 2, having reached southeast area; forged respond to these types...

  • Highlight the start of the execution wrought level 3 elevation -4.20 m. , -2 Ceiling basement, north, advancing at a rapid pace the implementation of Level 2 floors, having reached southeast area...

  • In northern area walls and supports the height reached level 3 -4.20 rise.
    Execution proceeds forged post-tensioned slabs based, namely concrete, prestressing and injection continuing the...

  • Focused on the implementation of the corresponding forged the basement ceiling -3, including the right jobs and injecting tensioning tendons of post-tensioned slabs Jobs.
    Highlights include...

  • Significant progress in the work with the concrete implementation of the first portion of wrought Level 2, elevation -7.70 m; include the type of this structure, post-tensioned slab, and its...

  • Work continues foundations, pile caps with the implementation of areas south, east and west, at the end of this July, would only run the pile caps for stands in the middle west.
    Note that...

  • It terminates the pilot phase belonging to the high bleachers and a half under ground, being run by the piles of high and low grandstand bleachers under and above ground respectively.
    ...

  • Work continues foundation either in their piloting in southwest and northeast areas, pile caps of south and west of the area under eaves comb.
    Anchoring Screen southern arm is complete, and...

  • The tasks related to the structure begin by running supports and walls, both in north, below ground.
    Also begins the implementation of sanitation north.
    Work continues in western pilot...

  • Continued implementation of the foundation based on concrete pile and pile caps in south.
    Anchors of the screen are made up of the first dimension platform - 4m.
    Begin using the new...

  • Work continues piloting, in the northwest of the stadium, concrete pile caps in south, has been completed the new ramp access to the work, and is preparing the working platform for execution of...

  • Work continues enforcement based deep foundation piles.
    Work continues excavation for location of pile caps, pile headed to retrofitted armor and concrete pile caps.
    Jobs in northern...

  • The work carried out correspond to the execution of pile caps north and southeastern and south pilot area, the excavation is being made in west alongside the existing installation location of...

  • Continuing to implement encepados north and northeast in frames belonging to high stands.
    Continue south pilotage area, and the pilot has been completed in southern arm screen.

  • Work continues in pilot area southeast, and executing large pile caps (up to 11 x 6.50 x 4.00 m, length, width and height) on north.
    Practically ended piles belonging to the screen south arm...

  • Work continues in northeastern pilot, has completed the implementation of micropiling and plinths for reinforcing interior footings, and implementation of the piles of the screen in southern arm...

  • Work continues in this pilot area and south as well as the reinforcement micropiling interior footings and plinths of the latter.
    Starting location of excavations for pile caps in north,...

  • Work continues Foundation: Pilot in northern and interior micropile reinforcement footings and plinths of these.

  • Completion of earthworks required for construction around the perimeter bowl of the middle and upper bleachers, and implementation of the access tunnels within this zone.
    Execution continues...

  • Work continues emptying excavation of land in the southern part of the stadium as well as the formation of the slopes provisional.
    Withdrawal of cabins on the existing bounds, and demolition...

  • Progress of the work of excavation in drain lands in eastern and southern areas of the stadium, and demolition work is continuing within the existing facility.
    Execution continues in...

  • Work continues drain land in the north and east of the stadium, and sloping provisional.
    Starting the deep foundation: foundation reinforcements micropiles in new foundations and in areas of...

  • Top work flows for the excavations to drain the lands on the north side of the stadium land, complete removal of the stalls in high stands and interior demolition work on the existing installation...

  • Appreciable changes are observed: removal of seats goes high stands, and ends the demolition of the lower tier until the skeleton stands tall.

  • Complete removal of low stands. Home removal of existing tier seats and interior demolition work on the existing installation.

  • Start of work with the work of removing low stands, lighting towers topple, clearing and removal of perimeter walls.