Work is progressing pilot for exterior foundation walls, pile running up to 50 ml. excavation; has begun headed thereof encepados excavation and concreting thereof.
Implementation of the slabs level 5, elevation +3.02 m starts., Corresponding to the area of boxes.
Ring post-tensioned slabs with level 3 concreting and grouting of the last tablet in southwest now complete, and has begun the same pit at level 4, level zero, in the north.
After the execution half frames absence of several stands in the south.
Work continues waterproofing and drainage Trados walls, and concrete supports and walls.